Just a quickie post ... I heard from Adrienne Pan that there were some fireworks at the open house for the contentious Bipole III transmission line, so I sent a correspondent down to have a look. It could be interesting to see a bunch of angry farmers, preferably with pitchforks, confronting Hydro managers.
I was disappointed to find out that everybody was quite civil. There were people who were unhappy, but no pitchforks and no yelling. However there was a sign that it might come down to violence if/when they start to build the thing:
The open house was to discuss the proposed west-side route only, not why it's going down the west side of the province. That didn't stop some people from asking though. Repeatedly. The poor hydro guy ... all he could do was shrug his shoulders and explain "It was a political decision. The east side was not an option."
It is clear that a pile of time, money and effort is being put into this project including 3D modeling of the whole route, fly-over style, using Google Earth Pro. Almost seems a shame to waste all of that effort by changing to the East route, as the PCs are planning to do if they get elected. Almost but not really. It is clear that the Hydro employees are trying to do the best they can with the parameters that they were given. I have no beef with them. Its the man at the top that I have a problem with.
Whelp ... that's about all I have to say 'bout that. Let's turn on the tube and see what Adrienne Pan has to say.
Monday, 8 November 2010
Bipole Disorder: The open house
Labels: Bipole disorder
Subscribe to:
Post Comments (Atom)
1 comment:
There is a federal approval required for the sale of power. I wonder where this is at? It is something that probably is going to be difficult to influence for the nice folks that are bringing us such astute planning
Post a Comment